Category: Scope Boundaries
Status: New Identified
Transferred to:
Risk Introduced to the Department: No
Risk Event: Without an approved final scope, there is a risk that the project will not be able to deliver for the December timeline.
Risk Cause: Scope document has not been signed off for approval.
Risk Context: Risk for December 2023 Release June 30: Have addressed comments from both CRA and HC, and have sent back to both departments for final approval.
Origin of Risk: Internal
Nature of Risk:
Owner:
Date Identified: 2023-06-19
Risk Consequence: Scope, Schedule, Cost, Benefits Realization
Risk Consequence Description: Without an approved final scope, there is a risk that the project will not be able to deliver for the December timeline.
Risk Impact Perspective:
Existing Control / Mitigation:
Current Probability: High
Current Impact: High
Current Exposure: HIGH
Risk Trigger:
Risk Trigger Date:
Risk (Score): 9
Response
Risk Management Action: MITIGATE (Requires Future Control/Mitigation actions)
Escalation Level:
Mitigation Plan Complete: No