Risk Description:
Due to the scale of operations that will be carried out within the WLM project scope, there is a risk that Tech Debt & BDM may overlap the WLM scope when working on their respective mandates. This could result in the same application being picked up by multiple groups if there is a lack of clear communication and planning.
Impact Description:
There is a risk that the scope and timeline are affected, also impacting the project costs.